Chat with Bali Zero on WhatsAppSetting up a PT PMA typically takes 4-8 weeks. Here's what happens in each phase and how to plan your timeline.
| Phase | Duration | Cumulative |
|---|---|---|
| Planning & Documents | 1-2 weeks | Week 1-2 |
| Notary & Legal Entity | 1-2 weeks | Week 2-4 |
| Tax & OSS Registration | 1 week | Week 3-5 |
| Bank Account | 1-2 weeks | Week 4-7 |
| Operational Permits | 1-3 weeks | Week 5-8 |
Week-by-week breakdown of the setup process
What might slow down your registration
| Feature | Document Issues | Name Rejection | OSS System Issues | Bank Requirements | Director Unavailable |
|---|---|---|---|---|---|
| Problem | Incomplete or incorrect documents | Company name already taken | System down or errors | Additional KYC/documentation | Director can't attend signing/bank |
| Delay | 1-2 weeks | 3-5 days | 1-3 days | 1-2 weeks | 1-2 weeks |
| Prevention | Double-check everything upfront | Prepare 3 unique options | Be patient, try again | Ask bank requirements upfront | Plan director's availability |
| Scenario | Timeline | Key Factors |
|---|---|---|
| Best Case | 4 weeks | All docs ready, responsive, good agent |
| Typical | 6 weeks | Normal processing, minor delays |
| Complex | 8+ weeks | High-risk sector, bank issues, delays |